Chapter 4 – Conditions on Network for Review of Application/ Reconstruction of Network
The total capacity of installed distributed generators (SSDG) on the relevant 22kV/0.4 kV or 6.6kV/0.4kV transformer exceeds 25 % of the LV transformer fuse capacity.
The total capacity of installed distributed generators (SSDG) on the relevant low voltage feeder exceeds 90 % of the feeder fuse capacity.
The capacity of SSDG at one customer terminal exceeds the capacity of the fuse at the existing customer terminal.
The capacity of SSDG at one installation exceeds 25 kW in certain areas.
The addition of an SSDG on the LV network, exceeds the total technically permissible SSDG connection capacity of the 22/0.4 kV distribution transformer or the LV feeder.
Reconstruction of the LV network shall be done if any irregularities are noted at the customer’s premises.
Applicant shall carry out necessary civil works (construction of cabins for housing meter, switch or laying of cables underground), as instructed by CEB, if required.