Chapter 4 – Conditions on Network for Review of Application/ Reconstruction of Network

  • The total capacity of installed distributed generators (SSDG) on the relevant 22kV/0.4 kV or 6.6kV/0.4kV transformer exceeds 25 % of the LV transformer fuse capacity.
  • The total capacity of installed distributed generators (SSDG) on the relevant low voltage feeder exceeds 90 % of the feeder fuse capacity.
  • The capacity of SSDG at one customer terminal exceeds the capacity of the fuse at the existing customer terminal.
  • The capacity of SSDG at one installation exceeds 25 kW in certain areas.
  • The addition of an SSDG on the LV network, exceeds the total technically permissible SSDG connection capacity of the 22/0.4 kV distribution transformer or the LV feeder.
  • Reconstruction of the LV network shall be done if any irregularities are noted at the customer’s premises.