Annex 5: Certificate of Installation

After completing the SSDG installation, Applicant/Installer shall submit a duly filled and signed "Certificate of Installation" to the CEB (available on the CEB website).

The certificate includes:

1. Equipment Details

  • Photovoltaic Modules (Make/Model, Rating, Quantity)
  • Inverter specifications (Output AC Rated Power, Serial Number)

2. Inverter Protection Settings

  • Over Voltage settings (230 V + 10% and 230 V + 6%)
  • Under Voltage (230 V - 6%)
  • Over Frequency (50 Hz + 2%)
  • Under Frequency (50 Hz - 6%)
  • Loss of Mains (df/dt - Vector shift)
  • Reconnection Time
  • Set Active Power Limit (if applicable)
  • Line impedance

3. Certification

The certificate must be signed by:

  • The Certified Installer (with company details and seal)
  • The Applicant
Important: This certificate certifies that the installation has been done as per the requirements of the SSDG Grid Code (Ver. 2.3) and includes a detailed schematic diagram.